A portable instrument runs for several minutes each hour. Bliley lists about 200 mW at startup and about 135 mW after stabilization for the LP62. Battery energy depends on time in each state. Multiplying steady-state power by a day or counting only active acquisition minutes can both be wrong. Include warm-up and any period the oven is held on after a measurement.
Draw one complete operating cycle first
For example, assume 200 mW for one minute, then 135 mW for nine minutes, and complete shutdown otherwise. That ten-minute interval uses about 0.0236 Wh. This is an illustrative integral, and actual startup power changes over time. Warm-up acceptance depends on starting conditions and allowed frequency error. For longer cold starts or powered standby, integrate the measured curve again.
Compare keeping the oven warm with cycling power on the same energy budget
For each strategy, log waiting time, when acquisition can begin, starts per hour and regulator loss. Keeping the oven warm can avoid repeated waits, while cycling can save energy during long idle periods. An immediate-trigger requirement limits latency even if cycling saves energy. Compare battery capacity in watt-hours or convert to a common voltage instead of dividing milliamp-hours at different voltages.
Power or instrument the clock branch separately, run the real workload for several cycles and then add other system loads. Confirm the exact part's guarantees and conditions before putting estimates into the plan. Typical brochure figures do not establish a full-temperature maximum. Bliley LP62 startup and steady-state power guidance