The final oscillator order and last shipment are six months apart. How many units do you need?

A discontinuation notice often contains several deadlines. A demand submission supports upstream material planning, the final order is the cutoff for accepting a purchase, and the final shipment affects inventory coverage. Waiting for the last shipment date can mean missing an earlier commitment. Some sales channels also ask customers to submit requirements earlier. Planning, engineering, and service need the exact ordering number and a forecast that extends through the last use of the original board.

Identify what each date governs

Epson notice 25-007E is a specific example for 5.0 V SG-8002CA/CE variants. It names three milestones for lifetime demand, the last purchase, and final shipment. The notice is dated September 12, 2025. Its schedule asks for demand information by December 15, 2025, lists last purchase at the end of June 2027, and last shipment at the end of December 2027. It says actual shipment may vary with order status. Those are notice fields. Confirm acceptance with the manufacturer or relevant channel for the full part number, current quantity, and schedule.

Other voltage versions in the family can have separate notices. Epson 25-006J gives different dates and replacement information for its 3.0 V, 3.3 V, and blank variants. If the BOM says only SG-8002CA, recover the manufacturer code, pin function, voltage, and notice number. A listed replacement points to a candidate for samples. Validate the old board's voltage, timing, land pattern, and load before switching. Put the required old-stock coverage and the replacement qualification schedule on one timeline.

Calculate against a stated horizon

Suppose the old board remains in production for 18 months at 360 units per month, one oscillator each. Field service consumes another 25 per month on average. At 385 units per month the forecast is 6,930. Add an approved 220 for trial builds and service variability, giving 7,150. Released inventory is 1,630 and confirmed inbound stock expected to arrive and pass in time is 1,020. The net buy requirement is 4,500. Leave quotes without an acknowledgement out of those offsets.

If only full 1,000-piece reels are accepted, order 5,000. Calculate the projected excess against the baseline as 1,630 + 1,020 + 5,000 minus 6,930, which equals 720. Of this, 220 is the approved reserve and 500 comes from rounding to a reel. Record them individually so the team can explain the overage later. Reuse the calculation when field-service demand changes. Past replacement records can help estimate service consumption.

Check when the buffer will arrive

Enough total inventory can still leave a gap before the final lot. At 385 per month, 1,630 released units cover about 4.23 months. If the 1,020 arrive at the end of month five, demand by then is 1,925. Before receipt the shortage would be 295. Planning can bring a delivery forward, change the order of builds, or switch early if the alternate has completed approval. Use monthly totals for an initial check and then plan weeks using workdays, holidays, inspection turnaround, and clustered service demand.

Define storage packaging, retest dates, and triggers for the long-lived final lot. For supplier-held inventory, agree on reel and lot visibility, the point at which ownership or release changes, and the records needed before shipout. Collect manufacturer materials documents while production is active if customers require them. The cited Epson notice warns that some chemical-substance information may become unavailable for discontinued products.

Give service demand a second scenario. Increasing it from 25 to 40 units per month adds 270 over 18 months. The 5,000-piece buy in the example still covers the increased baseline, with projected excess falling from 720 to 450. Reassess whether the 220-unit reserve still fits. If a new product also calls for this oscillator, track demand and replacement qualification separately. Otherwise new builds with another viable source can consume the final stock reserved for repairs.

Record the exit conditions

Keep the notice number, covered manufacturer codes, forecast date, confirmed receipts, and final reel count together. Update the same calculation after a qualification delay or a change in field demand. If the replacement moves ahead, review commitments already placed and whether the original parts can serve repairs. Confirm staggered lots against the specific dates and quantities. Use the actual allocation and schedule agreed by the supplier to decide what can reach each build.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.