One crystal quote is two cents cheaper. Does it still cost less per released part after screening?

Purchasing has two offers for the same specification. One goes through ordinary sampling. Its alternative needs an approved per-unit screen because the first shipment lacks sufficient process evidence. The second offer looks cheaper for 10,000 pieces. Count the releasable quantity, equipment, and effort. Both candidates must be eligible for evaluation. A low quote cannot waive required qualification for the specification or source.

Use releasable units for the same lot

ASQ's quality cost model distinguishes appraisal, internal failure, and external failure costs. Apply it to material, batch setup, per-part screening, and nonconformance handling. Production needs parts released to the work order on time. Inspection can delay setup and only addresses the items it measures. A room-temperature frequency screen does not establish startup, temperature response, or long-term drift.

Suppose both offers are for 10,000 pieces on equivalent currency, freight, and tax terms. Supplier A charges 0.42 yuan per part. Inspection and setup cost the buyer 60 yuan, and stores ultimately issues 9,970 for the example. Material and inspection total 4,260 yuan. Dividing by 9,970 gives about 0.4273 yuan per piece. This is an illustrative outcome. A sample cannot establish that every part is flawless. B charges 0.40 yuan per piece. Screening costs 110 yuan in setup and 0.014 yuan per part, or 140 yuan in variable expense. If 9,910 are released, total cost is 4,250 yuan and the unit result is about 0.4289 yuan.

Find the cost that would reverse the result

B saves 200 yuan in material and spends 190 yuan more on inspection, so up-front spending is still 10 yuan lower. After releasing 60 fewer, its cost per issued unit is slightly higher. At 9,910 released parts, B must keep the total at about 4,234.36 yuan to match A in this example. Subtracting its 4,000 yuan material cost leaves about 234.36 yuan for screening. These are hypothetical figures and exclude claims, delay, and downtime.

A variable test cost based on one second per piece can miss opening packs, recording reel IDs, and waiting for the counter. Trial the inspection and record handling, measurement, repacking, and verification. A chamber screen for repairs may use different setup and parallelization. Obtain actual changeover time and chamber capacity from manufacturing engineering. Distinguish supplier screening from receiving verification so neither gap nor duplicate work is hidden.

Account for reinspection, replacements, and delay

If a supplier replaces rejected material, the replenishment date determines when usable quantity returns. Ninety accepted replacements change the denominator, and prior labor, second-pass incoming work, and transport remain actual costs. Some contracts use credit and others require replacement stock. Record a financial adjustment when supported by its documentation. Remove destructive samples and trial losses from released quantity. If their material was already purchased, avoid adding that cost to the numerator twice. Preserve lot IDs for any return.

For a first qualification, run high and low yield scenarios against the build. If B delivers 9,910, check whether existing inventory covers the shortage and whether the customer can take partial delivery. A cheaper screen that misses the assembly slot does not suit that run. Use recent actual data for A as well and avoid treating prior yield as guaranteed. Record release dates and shortage response for both offers.

If the supplier offers preshipment screening, determine how results link to the units. An application may require per-unit records while the quote supplies only a batch pass count, leaving local verification. Check the same trial units at both stations and compare fixtures and rules before crediting the supplier's results. B can save money if any duplicate work is removed within the cost threshold and the method remains acceptable. Recheck the cost and methods if a customer changes limits. Results on an older package or frequency do not automatically carry over.

Add one line to the comparison

Use the same acceptance target and cost basis. Quality verifies the method, purchasing checks claims and replenishment, and planning records when stock can be issued. Under the quote, add material plus inspection divided by released units, with the trial record. A comes out slightly lower on this example. Actual labor and accepted quantity can change the result. Updating those inputs lets a buyer explain the decision without asserting unsupported yield or supply.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.