Specialist Supplier of Crystals & Frequency Control Componentssales@mecxtal.com.cn0755-26500570
MERLIN home / Rednote / Brands and Sourcing

The DP83867IR's 25 MHz crystal is delayed. Do 1.8 V and 3.3 V oscillators use the same connection?

A gigabit PHY uses a 25 MHz surface-mount crystal. The supplier offers 1.8 V and 3.3 V active oscillators at the same frequency. All three approaches involve XI, but they do not use the same circuit. Establish what refills the current BOM and what requires an assembly change. Begin with the DP83867IR/CR clock-input requirements independently of its other interface supplies.

Confirm the connections to XI and XO

Texas Instruments shows a 25 MHz crystal or oscillator in its typical application. Its crystal recommendation is a 25 MHz parallel resonator specified at 18 pF in the XI–XO oscillator loop. With an external clock, XO may be left floating. TI shows a direct XI connection for a 1.8 V clock and a capacitor divider for 2.5 V or 3.3 V. It recommends 27 pF each for CD1 and CD2 in the 3.3 V example. Check the XI electrical limits and consult the source supplier for applicable 2.5 V loads. Use the documentation for the exact PHY.

The reference design can also start with two 27 pF capacitors in the passive crystal circuit when detailed requirements are unknown. They form the crystal load network. The 27 pF capacitors in the external-clock example occupy different positions and divide a driven signal. Check the nets and component locations. List populated and empty positions by variant rather than applying both sets at once.

Compare the circuit conditions before using the same parts

Suppose two equal 27 pF capacitors load a crystal with an assumed 3 pF of effective parasitics. A simple approximation gives 27 divided by two plus three, or 16.5 pF. That is 1.5 pF below 18 pF. The parasitic value is hypothetical, and the calculation does not establish pulling or startup on TI's board. Check the actual crystal's load, maximum ESR, and drive. On the external path verify amplitude, bias, and transitions at XI. Its divider cannot be evaluated as though it were loading a quartz resonator.

The external oscillator table also lists 20%–80% edge measurements, 40%–60% symmetry, and an RMS jitter requirement with a 12 kHz to 5 MHz integration band. At 25 MHz the period is 40 ns. The symmetry range corresponds to a high time of 16–24 ns at the applicable threshold. Record the threshold and period. A different integration band on a supplier report calls for comparable data before qualifying the oscillator.

Test the source, XI, and link in order

Verify the complete candidate part, output format, supply, and control pin. Populate the actual assembly option and inspect the source and XI with appropriate probes. A passive branch left connected can load an external driver. For a passive assembly, use the approved measurement point to verify startup and reference frequency. Do not classify a crystal as out of tolerance after loading its pin with an unsuitable probe. Put the schematic revision and physical variant on the test record.

Check the link modes required by the product and repeat after resets and power cycles. If XI fails its requirements, investigate the source and network first. If the reference meets its requirements and the link still fails, proceed to PHY configuration, network connectivity, and the MAC interface. Use the passive board as a comparison. Verify external candidates across the applicable supply and temperature conditions, including enable and startup timing.

Compare the clock source and its supporting parts together. Existing crystal stock may not complete the current build if suitable capacitors are missing. For an oscillator at another voltage, verify the intended supply and that the fixture covers the new network. If both versions are in production, trace reels at receipt and board revisions at assembly so repair does not restore the wrong population.

Do not infer the XI rating from an I/O net labeled as a low-voltage domain elsewhere on the board. Compare the actual PHY pin's DC and AC requirements with the oscillator's loaded output specifications. For the capacitor network, verify the loaded topology. An unloaded test point does not reproduce the receiver. Ask for the conditions behind typical plots and obtain a relevant guarantee or approved test. Keep the result with the material record for subsequent builds.

The approval plan should identify failures missed by a room-temperature link test. A clock may disappear briefly before reset release and behave normally at equilibrium. Checking link several seconds after power can miss the first startup event. Capture when power enters its valid range, when reference clock becomes usable, and when reset is released. Keep options awaiting boundary checks on candidate status. If both paths pass, make approved schematics and population records available to repairs so the actual network follows the replacement.

Use one material record per clock path

Quote the passive variant with 25 MHz, 18 pF, ESR, package, and temperature. For 1.8 V and 3.3 V active variants, quote exact order codes and identify the schematic network and load. Check XI limits and the applicable noise specification before approval. Leave unverified options as candidates. The work order then tells production which fixture and network to use without relying on a shared 25 MHz top mark.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.