Equipment will be sold for five years and serviced for another five years after the final shipment. Asking how long the series has existed yields a history. The project needs to know which configurations will remain orderable, how discontinuation will be communicated, and how long boards can be repaired. In its discussion of long-term supply and lifecycle management, GEYER cites its earlier KX-C series and describes supporting old and new packages in parallel during a customer redesign. That gives purchasing a starting point for negotiation. Specific commitments still need to apply to the actual orders.
Plot the production and service demand for the same program
One curve represents production demand and the other represents warranty and spare-parts demand. For equipment that uses one crystal per unit, production deliveries can end while small repair orders continue for years. Ask planning for annual volume ranges, the final production date, and the expected end of service. Have the supplier confirm scheduling, minimum order quantities, and small-lot delivery terms for each exact order code. If the original service provider may exit, make sure the notice contact can be transferred to the party responsible for repairs.
Plan how to keep the old part available while a successor is qualified
Define the events that trigger notice, such as a package change, a key specification revision, or the end of order acceptance. For any recommended successor, agree on who provides samples and drawings, how the old part will remain available during qualification, and the separate last-order and last-ship dates. The design team should estimate time for a board spin or renewed customer approval. Even an on-time notice can leave too little time for validation.
At the annual review, compare the previous forecast, actual usage, and remaining spare stock on the same line. Count the supply arrangement as confirmed once the exact part numbers, each party’s responsibilities, and the applicable dates are agreed in writing. The series history from a web page is background for that record. GEYER long-term supply and lifecycle information