Specialist Supplier of Crystals & Frequency Control Componentssales@mecxtal.com.cn0755-26500570
MERLIN home / Rednote / Brands and Sourcing

When does production lead time begin for a custom KDS timing component?

A project manager asks whether delivery can happen in six weeks. The supplier replies that six weeks is typical. Scheduling depends on the start date, the delivery destination at the end of the period, and any outstanding milestones. Daishinku’s product FAQ says lead time depends on the product and specifications such as application and frequency. It also calls for discussing small-volume orders and minimum quantities case by case. A listed series name cannot establish the delivery date for a custom part.

Check whether the design inputs are frozen

Track the RFQ date, specification confirmation, sample shipment, sample approval, production order, factory shipment, and receipt at the destination as separate milestones. Ask the supplier to identify the start and end of the quoted interval and whether it requires a purchase order or approved drawing first. If frequency and temperature range are still open, mark the estimate as conditional and list changes that would require a new estimate. If sample and production dates differ, give the quantities for each so planning does not count a few engineering samples as supply for a full production run.

Work back from receipt to the latest approval date

Suppose the factory requires receipt by October 20 and allows one week for transport and incoming inspection. The shipment must then be arranged by October 13. If the quoted manufacturing lead time starts after sample approval, work backward to allow time for sampling and customer sign-off. State whether the calculation uses working days or calendar weeks and whether holidays affect it. Confirm the assumed logistics allowance for the actual project.

When an update arrives, keep its revision and the reason for the change, such as a pending suffix or a split first delivery. Show confirmed quantities and the outstanding balance separately on the production schedule. Pass a commitment to planning once the supplier confirms the exact order code, quantity, milestones, and delivery window. Daishinku purchasing FAQ

Send us a part number or your requirements

Brand, frequency, quantity and delivery target — a useful place to start.

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.