An oscillator is now NRND. What should happen to the existing board and the new design?

A device page now says NRND, or not recommended for new designs. The old board still ships and the next prototype was going to use the same oscillator. Record the two projects as separate decisions. Continued supply to the old board depends on the manufacturer's terms for its current customers, exact ordering code, and supply channel. Use on the new board depends on the validation plan and intended life. An available datasheet or distributor stock does not establish multi-year production delivery.

Epson's crystal and SAW lifecycle page separates NRND from the stages after orders stop or final shipments are pending. It describes support for existing customers and a later end-of-life notice. Renesas distinguishes EOL-notified parts from parts for which last-time orders are closed. These are manufacturer-specific processes. Review the formal notice and ordering code, confirm whether new orders can still be placed through an authorized channel, and check new-design restrictions. Leave any unconfirmed last-order date open.

Plan the existing board from actual consumption

List good stock, committed open receipts, forecast production, qualification parts, and repair spares. Reserve parts already promised to service before calculating production supply. Ask engineering when an alternate can be approved against the relevant board revision. Use current material issues and future work orders to estimate the bridge quantity. Consider lead-time or demand changes separately. When the manufacturer still accepts orders, check the actual terms and retain a justified transition stock.

For a new design, the decision follows BOM freeze and expected lifetime. Availability of ten parts can support ten prototypes without supporting years of production. Identify a candidate the manufacturer recommends for new designs and include drawings, clock configuration, and board tests in the plan. If the NRND part is used for a demonstration, identify the position and firmware dependencies that will have to change. Recheck supply status and ordering code before release. A chat message about NRND is easily lost across board revisions.

Worked example with two boards sharing one material number

Suppose the old board needs 1,000 devices a month for four months, service needs 700, and 3,600 are usable. Total demand is 4,700, leaving a gap of 1,100 before assembly loss and qualification stock. If a new lot is to qualify in month three, line up its release date with the schedule. A planned order cannot be used to fill the gap until its availability is verified. Confirm the manufacturer still takes orders and adjust the 1,100 for approved losses, actually available stock, and service policy.

Suppose the new board freezes next month and requires ten first-round units. Purchasing can find 20 old devices and use ten as build samples and ten for comparison. Engineering can designate the old part as a temporary prototype item while testing the preferred candidate. Work-order restrictions for the existing board should not spill into the new design. If both use the same internal material code, apply project approval restrictions to the new drawing. Recheck tests and supply at release. If the manufacturer advances the EOL date, recalculate the old-board bridge and keep the new design on its alternate path.

Put a review date on the item record

Store the webpage capture date, notice ID, status, projects, allowed use, order route, and next review date. Keep unconfirmed dates marked pending. If distributors disagree, get the manufacturer's answer on eligible orders. Lack of stock at one distributor cannot establish discontinuation. File last-time order and last shipment dates separately after the formal notice. Retain the supplier's committed volume, lot IDs, and use history so transition stock remains eligible when it arrives.

After the old-board change, check open reservations for production, repair, and buffers. Retain the old material for approved service applications and decide the surplus separately. Use the approved new code or candidate list in new drawings. Where service runs longer than production, manage a separate line with approved board revisions, original lots, receipt dates, and shelf-life checks. Confirm whether an order remains open for the original project and region. If a customer copies the existing circuit to a new part number, ask whether the manufacturer treats it as an existing program or a new design. Preserve the cited project and ordering code in the written confirmation.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.