Factory A transfers an unfinished reel of oscillators to Factory B. The reel label is legible, but the moisture-barrier bag was resealed. The receiving site needs the exact part’s moisture sensitivity level, its total exposure before resealing, and the treatment used at resealing. The manufacturing date is for lot traceability. Treating it as the opening date can unnecessarily quarantine usable parts or send overexposed parts straight to reflow.
Start by identifying the product family
SiTime’s manufacturing instructions list different storage and floor-life requirements by product family. Some products ship in a moisture-barrier bag with desiccant and a humidity indicator card. Purchasing should transfer the original label and full part number so the receiving site can identify the applicable instructions. Another series from the same brand may have a different rating. If the label and documentation appear inconsistent, ask the sender for the exact part’s packaging instructions.
Make exposure time calculable from the transfer record
Have Factory A record when the bag was first opened, when material was issued and returned, the shop temperature and humidity, and the conditions and duration of dry storage. Factory B should log bag integrity, indicator-card condition, and when it opens the bag. If the original opening time is unknown, document the gap and set the reel aside for a process engineer to assess against the applicable rating and instructions. A new label with today’s date cannot recover the missing exposure history.
When pretreatment is required, have process engineering confirm the limits for both the devices and the carrier reel. Some packaging may not tolerate the treatment temperature. After treatment, retain the record and remaining use window so planning can prioritize stock with the least remaining time. For small repair quantities, agreeing on smaller bag splits in advance can also reduce repeated opening and transfer records. SiTime manufacturing and storage instructions