A screenshot shows 2,000 pieces in the morning. Only half a reel remains when the order goes in that afternoon. The figure could describe a family, a specific orderable number, or stock already allocated to the buyer. Capture the evidence at three stages, when the seller queried stock, when the order was confirmed, and when incoming inspection released the parts. Those stages support different decisions about scheduling, booking placement time, and promising a customer a date.
Confirm the stock entry identifies the requested part
Get the complete manufacturer code, quantity, packaging, warehouse, and query timestamp. A search for 25 MHz or 3225 can aggregate different load capacitances, temperature grades, and packing options. Start at the family if necessary, and make the actual confirmation against the complete orderable number. The TI inventory API documentation distinguishes generic and orderable part numbers, and separates current inventory from estimated future supply. This illustrates how a family-level result can overstate the stock that applies to one part.
If a supplier uses two warehouses, ask what each can ship and whether a transfer has occurred. Two sales desks with access to shared stock can quote the same reel. Independent quantities require an actual allocation or independent stock evidence. A screenshot documents what was visible at an instant. A reel image identifies the photographed pack. An order acknowledgement can identify how many units were allocated to a specific PO.
Recalculate at each stage
Suppose 1,600 boards each need one oscillator. There are 280 released parts in the local warehouse, and a quote shows 2,000 in stock. Before supplier confirmation 280 can be issued, leaving a gap of 1,320. If the supplier confirms only 1,200 and gives an estimated dispatch date, eventual supply would be 1,480, still 120 short before losses. Planning can book a staged build and record the estimate as such. On an accepted order still awaiting shipment, check whether allocation is offered and how long it lasts.
When 1,200 arrive and inspection holds 30, released stock is the 1,170 available from the shipment plus the original 280, or 1,450. The gap becomes 150. Use the example to define fields consistently. Online stock, confirmation, transit, receipt, and release cannot be added together as one quantity. Separate entries show whether a gap is due to allocation, cancellation, a short shipment, or an inspection hold.
Get a status record that can be updated
TI's purchase-order guide distinguishes immediately available inventory and scheduled backlog orders. An oscillator PO can also track pending, partial, full, and canceled quantities with estimated shipment as a separate field. Give each schedule line its own date and quantity. Each required line quantity should link to a supplier acknowledgement and allocated quantity. If a sales reply just says the order is arranged, ask whether warehouse picking has started or production has an estimated date. Confirm packaging and any pending inspections.
Check the advance ship notice, carton count, actual quantities, carrier reference, and supplier part number after dispatch. A notice can exist before the carrier delivers. A tracking number can exist while the parcel is still waiting for carrier pickup. If 1,200 units are ultimately split into two cartons, record each carton quantity and arrival independently so the first carton does not close the line. A packaging or part change needs a new count of what can be accepted.
The same table can account for time. If expected dispatch is Tuesday and transit takes three days, arrival is Friday. With one working day for incoming inspection and a weekend shutdown, release cannot be assumed before the next workday. If the Monday shift issues parts early, check when inspection can finish. In an expedite request, specify whether the supplier should move up dispatch or delivery. Give production the expected release time. For cross-time-zone orders, keep both the supplier’s local time and the receiving site’s time to avoid shifting a date. A nearby pickup still needs a warehouse check. A pickup note and driver assignment document transport, while inspection establishes stock status.
Give production planning one usable count
An order reconciliation table can start with the exact part number and work order and carry the query time, confirmed allocation, expected dispatch, carrier status, and released quantity. The warehouse increases its releasable count after physical receipt and inspection. For outstanding commitments, planning should retain the latest supplier update and a deadline for deciding the build. If the deadline passes without a confirmed supply, reschedule against released stock or use an already approved alternate. Sales can still quote quickly, while production can see which commitment is supported.