Equipment can lose its external pulse-per-second reference soon after installation. Entering “24-hour holdover” for the Rakon ROD2522S2 can miss the training requirement. Its documentation says compensated holdover duration depends on cumulative locked time and can reach 24 hours. The longest guarantee requires 48 hours of cumulative learning. A freshly powered unit with an unstable reference has a different starting point from one operating continuously for days.
Turn the field use case into a timeline
From cold startup, mark when a reliable reference first appears, how long it is expected to remain, the first possible interruption and the equipment's allowed time error. An installation that starts in the morning and loses its reference that afternoon cannot be evaluated using holdover performance after two uninterrupted days. If factory training is possible, ask how transportation with power off, restart and reference changes affect learned compensation. Do not assume past learning survives.
Capture state changes and the final time error
Save input-reference validity, lock state, cumulative learning time and the exact reference disconnect time. Measure holdover time error against an independent reference and record the observation endpoint, ambient temperature and supply. If the PPS reappears but lock is not established, report the actual state. Signal presence alone does not establish that the required learning time has accrued.
If purchasing needs 24 hours of holdover after a short preparation window, submit that specific timeline to the manufacturer and reconsider the design if needed. Where more preparation is acceptable, make preoperation part of delivery and tell site personnel when the longest holdover condition is met. Rakon ROD2522S2 operating states and holdover requirements