An instrument must begin sampling within 25 s. Purchasing sees SCOCXOL advertised as fast warm-up and plans to use the existing 3.3 V supply. Micro Crystal's example criterion is entry into ±0.1 ppm at +25 °C: maximum 30 s for 3.3 V and 20 s for 5 V. Output startup is separate. A 20 s figure for the 5 V part cannot prove the existing board meets 25 s.
Determine how much of the 25 seconds is actually available to warm-up
From the power switch, regulator settling, oscillator warm-up, front-end reset, and first valid sample can overlap or run in sequence. Draw the actual critical path. A display that can start at the first clock edge has a different requirement from calibration that waits for frequency to enter a defined window. Specify allowed frequency error, measurement reference, and time origin so suppliers answer the same timing question.
Compare the full cost of a supply change
For the 5 V option, check startup current capability, receiver input tolerance, and whether level conversion or another regulator is needed. Compare warm-up and steady-state power separately. If field starts can be cold, request low-temperature data rather than extrapolating room-temperature times. Capture the supply ramp, ambient temperature, and time at which frequency enters and remains in the window.
For each supply version, list needed board changes, guaranteed conditions, and any remaining environmental verification. If board voltage is fixed, evaluate the feasible version instead of choosing it based on a time specified for the other voltage. Micro Crystal SCOCXOL supply and warm-up specifications