A supplier says the 20,000-piece order will be ten days late but it can ship 6,000 early. To know if that will keep the line running, find when the partial shipment becomes issuable stock, how much the line consumes before the next release, and which work orders can draw existing stock. Shipping, receiving, and quality release happen at different times. Calculate production coverage from the issue-ready date.
Diodes' sales terms describe partial shipments. SiTime's manufacturing notes give examples of reel quantities attached to packaging suffixes. Ask whether the supplier accepts a split, what minimum packaging quantities apply, and whether later installments can use the original terms. Verify the answers for your own order. An intact-reel requirement can make two or three whole reels the right first balance. If the supplier proposes a split reel, check leaders, traceability, and counting with the assembly plant.
Build a day-by-day inventory schedule
List each work order's start date, boards per day, oscillators per board, process allowance, and time materials are due at the line. Placement usually needs the complete batch before the day's build. Count physical good stock and remove complaint holds, retained samples, quarantined parts, and other reservations. For each shipment, separate carrier pickup, expected arrival, and projected quality release. Verify tracking, business-day receiving, and inspections. Friday dispatch does not establish Monday availability.
Allow for labels, reports, samples, and electronic component approval. Account for weekends, transport between regions, and retest. Confirm the partial shipment has the approved configuration. Distributor-programmed samples may have a different approval status from later factory production. Track the supplier's estimate and confirmed commitments separately and update availability when new evidence arrives.
Worked example: how long will 6,000 pieces last?
Assume 1,200 boards per production day, one oscillator per board, and another 20 for process use. The daily requirement is 1,220. Physical stock is 2,800, but 400 are reserved for repair, so 2,400 are available. Monday consumes 1,220, leaving 1,180 before the Tuesday shift, a shortage of 40. Even the full 6,000-piece partial shipment cannot support Tuesday as scheduled if it clears inspection that afternoon. Request release on Monday or move 40 boards to a later slot, after checking whether the work order can be split.
Suppose the first installment is available Tuesday morning, the final installment clears inspection next Monday, and this week runs five days. Demand is 6,100, so the first shipment must cover at least 3,700 after current inventory. At 2,000 per reel, order two reels. If daily boards rise to 1,400 and the allowance stays 20, demand is 7,100 and the shortage is 4,700. Three reels are now needed. Presenting both schedules gives the supplier a target tied to the actual build.
Include internal transport when two contractors draw from a central warehouse. A reel released in the morning may still miss the morning shift if the next truck leaves in the afternoon. Check that both reels can go in one shipment and that no report delays one of them. If the supplier uses another qualified lot, check revision, packing, and any work-order restrictions. Assign known reels to the work orders they can support. Recheck availability at the bottleneck date after the total quantity is agreed. Treat weekend production and receiving calendars individually when they differ.
Recheck the tail after receiving the first shipment
Record the full code, installment quantities, packaging, committed ship dates, and documents. Preserve the original order balance, settle each receipt against its own inspection, and show scheduled receipts that are not yet released. If two lines share the early stock, prioritize the work order with an immediate complete-kit requirement and then follow the actual schedule. Align the contractor's issue cutoff with the warehouse's.
Once the first release is complete, calculate the remaining stock and work orders again. A changed customer sequence or another delay changes which order is first affected. Identify the first date inventory goes negative and the corresponding work order. A useful handover shows what each day starts with and the specific, verified reel receipts that are due.