Putting 150 °C and frequency limits on the same TXC A3 40 MHz crystal order

The existing approval for a 40 MHz automotive crystal names TXC’s AV family. A board passes at room temperature, but the thermal review calls for a higher local operating temperature. The supplier provides the A3 page, with the same nominal package outline, and highlights both +150 °C and ±15 ppm. Copying both figures to one item can turn separate family features into an assumed combination. Identify which board functions need to work at high temperature, and obtain the part number, frequency tolerance, and measurement basis for that precise temperature range.

Translate catalogue fields into an RFQ

TXC’s automotive MHz crystal catalogue lists AV at 3.2 × 2.5 mm, 8 to 62.4 MHz, with operating temperature options up to +125 °C. A3 has the same nominal planar dimensions, an 8 to 40 MHz range, and a −40 to +150 °C option. TXC uses G0 for that range in its automotive selection presentation. The A3 product row lists multiple stability values, including 15, 30, 50, and 150 ppm. It does not give every frequency and temperature combination. To evaluate a 40 MHz crystal at +150 °C, ask for written stability, load capacitance, drive, and maximum equivalent series resistance for an exact orderable part number.

A quote that says 40 MHz and 15 ppm and one that says 40 MHz and G0 are incomplete for comparison. Give initial tolerance and temperature stability separate fields. Request the reference temperature and guaranteed or typical status for the first, and whether the second is change from room temperature or total offset from nominal. If the supplier provides automotive qualification evidence, check its scope against the exact part. Compare height, terminal configuration, and recommended land pattern on the actual drawings. The same nominal AV and A3 footprint dimensions do not establish mechanical or electrical interchangeability.

Convert the high-temperature allocation to hertz

Suppose a system permits 70 ppm absolute error at 40 MHz under its hot condition. That is 2,800 Hz. If a supplier confirms 10 ppm initial tolerance and 50 ppm temperature change from room temperature, a same-direction worst case spends 60 ppm or 2,400 Hz. That leaves 400 Hz for aging, board load error, and other relevant budget terms. If the confirmed temperature term is 150 ppm, it alone permits 6,000 Hz of error and exceeds the system limit. These values illustrate the budgeting method. Use the exact manufacturer configuration for the purchase.

If a calibration cancels some room-temperature error, verify when that correction is applied after a power cycle, board replacement, or derated operation. Suppose calibration lowers the maximum residual from 400 to 100 Hz and the temperature term stays at 2,000 Hz. Using a worst-case sum increases the theoretical remaining margin from 400 to 700 Hz. Calibration does not remove the temperature term or change the component agreement. Send any quotation with a different stability basis back to engineering with the approved calibration conditions. For a design that changes configuration as temperature rises, verify that the transition occurs in time.

Match hot testing to the purchase requirements

Record temperature positions and timing for pilot assemblies. If the maximum external ambient is 120 °C, the reference location near the crystal is 18 °C warmer, and the project adds 4 °C for measurement and repeatability, the selection point is 142 °C. This is 17 °C above the AV catalogue’s upper limit and 8 °C below the top A3 option. Confirm the manufacturer’s temperature definition. Record chamber and board measurements, stabilization criteria, and the frequency counter reference. For a short hot exposure, specify its duration, allowed loss of functions, and recovery conditions. A room-temperature reading after heating cannot establish that the board met requirements while hot.

At pilot, ask for supplier measurement conditions at both grades and traceable sample identifiers. Keep startup failure, late startup, and steady-state frequency error as separate outcomes. If nine of ten boards meet the frequency window and the other cannot start, record the startup failure against the tested group of ten. Retain the board number for every repeated attempt. The frequency distribution describes only the boards with valid outputs, while the complete register supports a separate judgment about starting and stopping when hot.

For production first article, confirm the approved 40 MHz crystal and capacitor configuration. Record the room-temperature frequency, then check frequency, startup, and affected downstream functions in the agreed hot conditions. Retain absolute error and change from room temperature against their respective criteria. If the quote cannot confirm temperature and stability together, keep the order at engineering-sample quantities pending written limits. When temperature is covered but the frequency margin is insufficient, engineering can revise the functional budget or design before sourcing a candidate. Link the purchase, assembly, and inspection records to the same part number and conditions.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.