Manufacturer guidance
Under Mounting, KDS recommends avoiding ultrasonic welding in assembly or processing. Excess vibration can reach the crystal, degrade its characteristics or prevent oscillation. This guidance is about the process and provides no universal limit derivable from frequency, package size, or previous cleaning results.
Review the mechanical path
Cleaning, welding and other vibration processes can couple energy differently. Map the connection from the weld to the crystal through the PCB, fixture, housing and other parts. Distance alone cannot establish safety.
Keep the weld location, assembly sequence, fixture constraints, equipment and process records. Do not infer permissible power, time, pressure or other thresholds from a package drawing. A device with no visible cracks can still have changed electrical characteristics.
Verify the new process
Under conditions agreed by the project owner, compare function, start-up and required electrical characteristics before and after processing. Retain unprocessed controls. Set the sample size and acceptance criteria in the project specification.
Limit findings to the recorded station, process and hardware revision. Reassess if the crystal, PCB, fixture or assembly sequence changes.
| Check | Record | Scope |
|---|---|---|
| Process | Cleaning and welding separately | Validation cannot be transferred automatically |
| Mechanical path | Crystal, PCB, fixture and housing | Distance alone is insufficient |
| Process record | Equipment, settings, station and sequence | Use documented limits |
| Validation | Before/after results and untreated controls | Applies to the tested configuration |