One parameter on a delivery is outside the order tolerance. Engineering and the customer approve 300 devices for one pilot run. Three days later, the warehouse still has parts from the same lot and the contract manufacturer has work in process. Before the temporary approval expires, planning needs to know which reels can still be issued, what happens to loose stock, and whether completed assemblies can proceed. Put the authorized quantity, application, deadline, and traceability conditions in the inventory process, so the final decision can use actual consumption. Terms for the approval include concession, special release, and deviation approval.
Bosch's public supplier quality manual describes its own procedure in section 10. If the supplier cannot meet specifications, it must obtain special release before shipment. The request identifies the deviation and the quantity or period involved, and the delivery has agreed identification. Use that as an example of the fields to request. For a different project, follow its own rules for the responsible approver, additional customer sign-off, and timing.
Make each operation honor the signed limit
Record the specification page, deviation, applicable conditions, production lot, and physical reels. If the deviation involves frequency stability, specify whether it concerns initial room-temperature tolerance, a shift relative to a reference temperature, or the full range including other effects. List the temporary shipment or screening criteria and tie the samples to the production stock. If approval covers only one board revision, position, or use, apply the same boundaries to the stock record. Engineering and quality should sign the volume, eligible work orders, and deadline against real stock and the build schedule.
Define the deadline by event. An approval through Friday at 18:00 could mean the last warehouse issue, the end of placement, or a customer delivery cutoff. Each produces a different disposition for parts at the line and work in process. Align the shift clock with the approval. Before issue, show the eligible work order and remaining limit. Scan the part to confirm the deviation record and test that an over-limit issue would be rejected. When several contractors issue parts, each issue draws from one approved total.
Worked example for an allowance of 300 parts
Assume one production lot has 1,200 units and quality allows 300 for an indoor pilot board. The normal and service orders use the same internal part number. Before receipt, have the supplier designate a traceable 300-piece child reel and record its parent. Book that reel separately and keep the other 900 on hold. Suppose placement must be complete by the deadline, and assembled boards may proceed within specified final-test and use conditions. The line receives 300. A new work order cannot extend the permission after it expires.
At 18:00 there are 240 installed devices, 12 used in testing or setup, and 48 left at the line. The sum is 300. Hold the loose 48 by reel and work order. Check for opened packaging, mixed stock, and stray pieces. Preserve board serials, placement timestamps, and the approval ID for the 240 assemblies. Handle them under the final inspection and use defined in the approval. Keep the original 900 and returned 48 separate. Their packaging, placement, and recovery histories differ.
If the inventory record says 245 were mounted but the machine boundary and first-article record support only 240, investigate the difference of five. Missed picks, manual placements, and counting errors are possibilities. Hold a board if its completion before the cutoff is unproven, and have production reconstruct the order history for the approver. If the document instead limits the issue date, use its rules for the 48 already issued but not mounted. Submit an extension separately if needed, with the pilot evidence, original request date, and actual usage intact.
For multiple customers, test another work order that shares the part. One customer's approval covers the specified revision and end use. If sales wants to redirect the pilot boards, have quality confirm the new use in writing and retain the serial list.
Close the record and reconcile actual stock
Reconcile returns, scrap, additional approval, and unlocated balances under project rules. Photograph the label and packing of child reels being returned. If rescreening allows normal receipt under the original specification, preserve the authorized procedure, acceptance criteria, and label mapping. Review each reel so that restoring screened stock does not release the other 900 in bulk. Physically clear short tape strips and manual replenishment boxes from the contractor. Verify the source of any replacement used to repair an approved board.
Test two actual orders to close the record. A valid pilot serial should show its inspection and permitted use. A new service order for the same internal number should receive only eligible inventory. File the signatures, line details, and supplier's return-to-normal evidence. A later deviation covering a new lot or new use needs its own approval.