A custom-frequency oscillator quote says NCNR. What should be fixed before ordering?

Engineering wants an oscillator at a nonstandard frequency. The quote has a long lead time and is marked NCNR, generally meaning non-cancelable and non-returnable. The prototype is still being tested, and a production order could leave excess stock. Identify what can still change: frequency, options, volume, or the customer schedule. Separate identifiable engineering samples from production when the specification is unsettled. If the specification is stable but demand is uncertain, ask whether production, delivery, and quotations can be staged. Obtain the applicable milestones in writing.

Diodes' standard sales terms discuss cancellation, order changes, and partial shipments separately. SiTime's FAQ describes different programming paths for engineering samples and factory output, and it provides a sample request channel. Use these public examples to decide what to ask. The quotation, purchase order, and actual acknowledgment determine the terms of a specific order. Confirm which lines NCNR applies to, when it starts, and what happens if price or dates change. Review any new restriction in the sales acknowledgment before accepting it.

Freeze the identity of the part you expect to receive

Specify the exact frequency and unit and check how the manufacturer treats decimal places. Record signal interface, power supply, enable polarity, temperature range, and accuracy. If the distributor programs samples, preserve their configuration and identity. Verify which electrical evidence and orderable identity carry over to manufacturer production. Link the approved specification to the order, and keep working drafts separate from production instructions.

List all decisions that can still move. Record sample quantity and date, test deadline, specification freeze, customization start, final change date, and staged acceptance, with a named owner for each. An estimated ship date may not tell you when material commitment becomes irreversible. Ask the supplier whether it is possible to delay or revise. Even if a manufacturer already has standard blanks, get written confirmation of when the custom order actually becomes committed.

Worked example with 200 pilot units and 4,000 possible production units

Suppose a pilot needs 200 units and production in six weeks might need 4,000. Customer tests are open. Frequency is provisionally 127.9875 MHz and there are two candidate temperature ranges. The supplier agrees to deliver 200 samples with an identifiable configuration and issue a separate quote for 4,000, with production accepted only after temperature sign-off. Order the 200 for the approved purpose and verify they do not trigger the other 4,000. After testing, sign the controlled specification, confirm customer volume, and place the production order. If the lead time exceeds the build slot, give planning the quantity and timing at risk. Ask about preparation of common material and any actual commitment it requires.

Another offer might require committing to all 4,200 at the outset, with no cancellation after customization begins. If the customer stops after the 200-unit pilot, 4,000 remain. If the temperature range is still open, the exposure includes a wrong option as well as excess volume. Ask about splitting the order and budget the realistic demand. If a single binding order is needed, record the remaining quantity and delivery responsibility in the approval for the project, purchasing, and the authorized approver.

Staged delivery may leave the commitment unchanged if the whole run starts at once. Track whether material has been started, whether another project can use it, and which lot will ship first. If the supplier does not disclose its process, obtain the last date for changes and the possible fees in writing. Record the response date and budget both the original and delayed schedules. Use the effective signed documents for the contract review.

Handle quality problems separately from schedule changes

Confirm whether NCNR covers buyer-initiated planning changes and whether the order has a separate quality-return procedure. Record wrong ordering codes, out-of-spec results, and transit damage under the agreed requirements. Verify the return route with the seller and quality representative. On the order, distinguish the original commitment, approved volume changes, and a quality dispute. Count excess material against another order only after confirming its specification and actual demand.

Before production commitment, match the version under test, full ordering code, approval, quantity, and deliveries. A clear distinction between committed and pending quantities protects the engineering schedule more than a verbal promise of early shipment. It also tells the next buyer which pilot request can still change and which order has passed the commitment milestone.

References

WeChat

MERLIN · TIMING COMPONENTS

Scan with WeChat to contact Sales

Add our WeCom contacts from your usual WeChat app.

On desktop, scan with your phone. On mobile, save the QR image and select it from your album in WeChat Scan.