The manufacturer website lists a higher impedance limit than the approved specification in the purchasing system. The supplier says the page was updated. Establish which revision actually governs the ordering code and who approved the change before editing the system. A product page, catalog, delivery specification, and customer drawing can cover different scopes. A new series option may leave the existing order untouched. A formal limit change from a specific lot may require project review.
NDK's crystal catalog explains that catalog specifications are for reference and asks users to check delivery specifications issued under the contract. Build that distinction into the purchasing procedure. A family page can cover several frequencies, loads, or outlines. Trace each parameter to the device sold under the full code. Check revision, effective date, and suffix coverage even in a model-specific datasheet. A tighter project requirement needs manufacturer acceptance in the agreed documents. An internally adjusted limit cannot silently become a condition of a standard part number.
Make the four-way comparison
List the parameter and measurement conditions, effective manufacturer delivery specification, existing approved revision, and current supplier explanation. Cite page or table numbers. Separate initial frequency tolerance, temperature stability, and total accuracy including aging. Bring drive and load conditions into line before comparing impedance. Verify the exact package and temperature range. The differences can then be assigned to specific incoming lots.
Ask for written manufacturer confirmation of the change type. It might be a page correction, a typical-value update, a change in guarantee, or a cross-reference to the wrong part. Correct internal material referencing an erratum. For a guarantee change, check the change notice, first affected lot, shipment timing, and customer approval. Link the effective decision to the actual stock. Retain old records and put an unambiguous specification number, date, and code on the order.
Worked example with 40 Ω and 60 Ω
Suppose delivery specification S sets a maximum equivalent series resistance of 40 Ω at the specified condition. The series page lists up to 60 Ω. The manufacturer confirms the webpage represents the broader family and the ordered code still ships to S. A new sample reads 52 Ω. Confirm the instrument, drive level, and other conditions. If the result is valid and reproducible, the sample fails the 40 Ω criterion. All these values are illustrative and must not be transferred to a real model.
In a different case, the manufacturer confirms a change to revision T and says production has switched. If the project has yet to approve it, follow the existing hold or deviation process. Engineering checks startup margin. Purchasing asks whether the stricter option can still be supplied. Quality determines how finished products and repair stock will be identified. If necessary, ask whether the strict grade has its own ordering code. Once T is approved, change inspection limits with a clear start point and an approved use rule for old stock. While awaiting confirmation, hold affected receipts and release separately identified reels with a verified revision and evidence that they meet the original requirement.
Make the right revision visible for every lot
Review stock accepted under the old revision and outstanding orders before scheduling the transition. If the internal code is unchanged, apply receipt-level attributes tied to manufacturer lots and first deliveries. Include specification number and revision on inspection records and preserve measurement units and method. A supplier's old webpage printout can then be reconciled to the controlled document actually agreed at the time.
For engineering samples supported only by a public series page, verify the stated electrical range in the intended design and ask for the controlled specification before production. Follow one order through the product code, customer drawing, manufacturer acknowledgment, original reel label, and receiving criterion. Add the missing mapping where any step uses only a generic material name. The next measurement between two apparent limits should have a clear controlling document and a known owner for board-level reassessment.
A contractor may hold the supplier drawing, the customer may hold the equipment drawing, and engineering may reference an older test method. Identify each approval owner. Update the controlled file and review dependent references. Avoid asking inspectors to choose whichever number seems strictest. Check any unit conversion with a known specimen. When two limits must temporarily coexist, assign them by lot and issue a controlled disposition. After approval, record the retired revision and which work orders remain on the earlier rule.