A company uses two oscillators with the same nominal frequency and package. The wider-tolerance version is approved on a standard board. The tighter-tolerance version passed validation on the standard and high-accuracy boards. The standard build can use the tighter part within its approval, while the high-accuracy build cannot use the wider part. Putting both into one unrestricted substitution group can make the total look sufficient when usable stock differs by board. Define alternatives by board revision and reference designator.
The Microchip DSC1001/3/4 datasheet lists different stability options and specifies frequency, temperature, package, and other codes in its ordering rules. Before accepting a tighter option, check the interface, operating range, and board validation. A stability grade does not identify the whole device. SAP's BOM guidance associates alternative items with specific BOM positions and separates issue priority, strategy, and usage probability. Its manufacturer part approval example can restrict by plant, validity, revision, and manufacturer location. Use those published examples to understand the engineering records, even if your software uses different fields.
Define the two use points explicitly
On the controlled BOM, record the board, revision, position, and full primary ordering code. Retain the approved alternative's manufacturer code, test evidence, and restrictions separately. The high-accuracy position lists only the approved tight grade. The standard board can use the wide grade first and list the tight one as approved. If both derive from a common BOM, verify that the high-accuracy variant excludes the wide grade. Separate internal codes can also be appropriate. Show the actual part identity at issue so a generic pick description does not allow a mix-up.
Verify approvals by plant. A part used at one site may still lack customer or process approval at another. Ability to buy a part and permission to use it on a work order are separate records. Purchasing may retain a common vendor list. Production should use the actual revision and approved scope. Track time- or quantity-limited substitutions and block issue at expiry. Check packaging, orientation, inspection, feeder, and placement with the physical parts.
Worked example with 1,000 parts in stock
Suppose 600 tight and 400 wide devices are available. The high-accuracy order requires 500 and the standard order 480, one per board. Reserve 500 tight parts for high accuracy. The standard order can use 400 wide and 80 tight if the project and process permit both approved types on the same order with traceable segments. Both orders can then run and 20 tight parts remain. At reel change, record actual ordering code, position, and board ranges so a lot query identifies which grade was installed.
If the standard customer requires one code per work order, its 400 wide and the remaining 100 tight each fall short of 480. Confirm whether two traceable work orders are allowed or obtain at least 80 more wide parts. Avoid borrowing from the high-accuracy reserve without a confirmed plan. One SAP example checks alternatives in priority order and selects an item that can cover the full requirement. Such a strategy need not combine the two grades automatically. If using it, test split orders and actual issue availability before calling the 1,000 pieces sufficient.
Returns need the same rule. If the standard board returns unused tight parts, book their actual ordering code, lot, and packaging state. Receiving them as the standard wide-grade primary hides stock the high-accuracy build could still use.
Test the setup with three orders
Before release, simulate a high-accuracy order offered wide parts and confirm that the system blocks them. Try a standard order within wide-grade availability and check the preferred issue. For a third standard order with insufficient wide stock, confirm that the approved rule either uses tight parts, splits the order, or reports a shortage. When plants approve different brands, include a plant where the alternative is not released. Inspect purchase orders, issue scanning, production records, and finished-board traceability, not just the selection list.
Also agree on planning treatment. If the tight grade is only an emergency alternative for the standard board, a fixed purchasing ratio may be inappropriate. Check what a zero usage probability means for planning and whether work-order issue is still allowed. Rerun the three cases after a site transfer or revision change. The planner needs to know how many units are reserved for each board and how much inventory is eligible for the balance.
References
- Microchip DSC1001/3/4 datasheet, Features and Product Identification System
- SAP Help, Data for Alternative Items, priority, usage probability, and issue strategy
- SAP Help, Using Alternative Parts, priority and full coverage by a single part
- SAP Help, Approved Manufacturer Parts List, purchasing plant, revision, and validity